The charger itself is the cheapest part. The install is an electrical project: panel capacity, a 240V circuit, a permit, an inspection. Here's what actually happens, in order.
Quick answer: Level 2 install stack: charger $400–800 · installation labor $400–600 · 240V circuit/electrical $500–1,000 · permit $200 = $1,500–2,500 total. Panel with a spare 40–50A slot: no upgrade. Full panel: +$1,500–3,000 or load management ($400–600) instead. Federal tax credit: 30% up to $1,000.
Step 1: the panel check
- Open your panel: need one spare 2-pole slot (40–50A breaker)
- 200A panel: almost always fine without upgrade
- 100A panel: load calc needed — may need upgrade or load management
- Full panel but adequate service: load management device ($400–600) pauses car charging while the range/AC runs — cheaper than a new panel
Step 2: the circuit run
The electrician runs a 6 AWG (48A) or 8 AWG (40A) circuit from panel to charger location. Cost driver is distance: $500–800 typical attached garage, $1,000–1,500+ detached garage or long runs through finished walls. Trenching to a detached structure adds $10–25/ft.
Step 3: permit and inspection
240V circuit = electrical permit ($100–300, often pulled by the electrician) + inspection. Hardwired chargers require it; plug-in (NEMA 14-50 outlet) installations sometimes don't — but skip the permit and you're exposed on insurance and resale. Just get the permit.
Charger pick: hardwired vs plug-in
Plug-in on a NEMA 14-50 outlet ($50–100 outlet): portable, replaceable, no electrician needed to swap chargers. Hardwired: required for some 48A+ units, marginally safer, fixed. Most homes: plug-in 40A unit on a 14-50 — flexible and upgrade-friendly. Get a UL-listed unit with a 25-ft cable and Energy Star rating.